Loading...

Proceeding
Sno Hearing Date Procceding Next Hearing Date & Time Status
1 11-12-2020 Hearing held through video conferencing.

No one present for respondent.

Shri Abhinav Kardekar, Counsel for CSPDCL.

Shri S.R. Dhruw for CEI.

2. Submissions on behalf of CSPDCL filed today. Copy given to the other parties.

3. The case be listed for final hearing on 07.01.2021 at 3:30 PM.
07-01-2021
15:30:00
Under Process
2 07-01-2021 Hearing held through video conferencing.

No one present for respondent.

Shri Abhinav Kardekar, Counsel for CSPDCL.

No one present for CEI.

2. Heard him. He admits that cross subsidy surcharge from the generator for FY 2018-19 has been received by the CSPDCL.

3. From the records, it appears that, the data submitted by the Chief Electrical Inspector on 13.02.2020, to the Commission, is accepted by the respondent Ms ACB (India) Ltd., with modification that captive consumption 31.518 MU is 14.17% of net generation with respect to 30 MW only because there are two separate entities of 30MW each and the captive load was met out of the 30MW old unit only.

4. It is also submitted that for supplying power to own captive load (after restoration of unit), cross subsidy surcharge was paid to CSPDCL on the unit consumed as per the CSERC Regulations.

5. Considered the submissions of the parties and keeping in view the admission made by the CSPDCL counsel, there is no need to proceed further hence, the petition is disposed off accordingly.
---- Disposed