1 11-12-2020 Hearing held through video conferencing.

Shri Pradeep Tandon, President, Shri Ajit Rai and Shri S.K. Pal for respondent.

Shri Abhinav Kardekar, Counsel for CSPDCL.

Shri S.R. Dhruw for CEI.

2. Submissions on behalf of CSPDCL filed today. Copy given to the other parties.

3. The case be listed for final hearing on 07.01.2021 at 3:30 PM.
07-01-2021
15:30:00
Under Process
2 07-01-2021 Hearing held through video conferencing.

Shri Pradeep Tandon, President, Shri S.K. Pal and Shri Ajit Rai for respondent Ms JPL.

Shri Abhinav Kardekar, Counsel for CSPDCL.

No one present for CEI.

2. From the records, it appears that, the data submitted by the Chief Electrical Inspector on 13.02.2020, to the Commission, is accepted by the respondent Ms Jindal Power Limited (JPL) and informed that they have supplied 6.56MUs power to South Eastern Coal fields Ltd. (SECL) to their Gare Palma IV2 IV3 Coal Mines for FY 2018-19. It is also submitted by the respondent that cross subsidy surcharge for the supplied power had already been paid by SECL to CSPDCL directly. For such power supply, NOC was granted by CSPDCL.

3. The CSPDCL admitted that upon their NOC, 6.56 MUs power was supplied by the respondent JPL to SECL and cross subsidy surcharge for the supply has been received. The counsel of CSPDCL is confirmed the admission during arguments.

4. Considered the submissions of the parties. There is no need to proceed further hence, the petition is disposed off accordingly.
---- Disposed